Monday, December 10, 2012

Framed!

We have been framed!
Well the outer walls of the house have been. That's what we've been doing this week.
 Each section had to be measured cut, assembled, screwed and lifted into position. With this Supra frame system, there are no noggins only studs. Up to 3 studs are fitted to door openings and 2 to windows. Now lifting two studs is pretty easy as is 2 lengths of U channel. Add up to 12 studs and U channel and they become HEAVY.
4 of the openings were full of studs and a large opening for a sliding door the walls are also 3 metres high. To put them in place we had to slide them out onto the verandah and raise them to fit between the roof purlins and the end of the main beams.
We fitted all the other openings and figured that the Feral Fossils needed help with these.
Turns out that when the brawn department ain't up to it the brains have to take over.
So we propped the top of the wall on the ladder (the Transformer - thanks Olwen) and were able to lift the panels and slot them in. Took about an hour to fit them and screw them off.
Not bad for a couple a fast approaching geriatrics!  
 

 John came out today with some more metal and an inspection. A few adjustments, but he gave us both an elephant stamp.
Tomorrow we start on the internal walls.
 

3 comments:

  1. Really enjoy watching your progress. Must be very satisfying end of day.

    ReplyDelete
  2. Wow, it's really looking like home now, isn't it1

    ReplyDelete
  3. It is looking really fab... a real house! You guys are amazing!! What a pair of achievers!
    Jenni

    ReplyDelete