Thursday, November 22, 2012

Putting a Roof Over Our Heads

Yesterday it began, to define the shape of our house with the addition of the custom orb roof, which is a fancey way of saying corrugated iron!

   
The first of the verandah sheets go down.
There are 48 sheets to both verandahs and every one had to be cut down. The Feral Fossil A team was set to work cutting the ends and passing them up to John who only came down from his lofty perch for coffee.
By lunch time the front veranda was done. The back was completed by around 3pm.
 This morning we sat on the back verandah and had breakfast in preparation for the main roof.

 

Tuesday, November 20, 2012

A $200 Hole

Back in September our next door neighbour and our neighbour but one, organised with a local farmer to bring in his dozer and do some work. Were we interested?
You betcha!
We had a spot on the driveway earmarked so we set him to work.
 With much roaring, belching of black smoke and clanking the hole grew deeper and the banks higher. Ended up about 2.5 metres deep in the middle. Lindsay said he thought it should hold water as there was plenty of clay, but our enemy was evaporation and seepage.
In order to compact the base and walls, Jim first tried the old ute, but the long wheelbase meant it kept bottoming out. So the trusty Discovery was pressed into service. Jim drove backwards and forwards up the walls until he felt that it was compacted as well as we could manage.
As will anything involving earthmoving equipment the site was raw and rather an afront to the surrounding bush.
A layer of bark chips over the top of the bank and a few tufts of local grass helped to soften it. 
 Then we waited for rain. Our catchment area is a section of drive about 3 metres wide and 100 metres long. This should give us about 300 litres for every mil of rain that falls. First event yielded us a small puddle in the bottom and we stuck a stick at the water's edge and waited to see if it vanished, but a week later and the water level had not dropped very much.
Next rain event and the level rose higher and stayed constant.
This week we have had good rain from thunderstorms and the dam now look like this. The next lot should reach the spillway.

In my mind I see it as a limpid pool with our local blue waterlillies, rushes grasses and other small sprawling plants on the bank. It will be a work in progress for quite a while, but will be a lovely spot eventually.
Not bad for 200 bucks eh? 

Friday, October 26, 2012

Wednesday, October 24, 2012

More Nesting Material

After a gap of me being away for 2 weeks, and Jim finishing the verandah decking on his 'pat malone', the next load of materials arrived.
The roofing/cladding, guttering, ridge capping and the flooring. John gave us a lesson on installing the verandah rafters, then on to laying the flooring.
 Got 1/3 of floor laid, glued and screwed by 4pm.
Now, most constructions use 'yellow tongue', a much lighter material, This construction in keeping with the 'industrial strength' theme is in 'red tongue terminator. Much thicker, denser termite resistant, and naturally HEAVIER.
See how the Feral Fossils go tomorrow on our own . . .

Sunday, September 16, 2012

Flooring #2

 Treated pine decking going down on the front verandah
One half of the 'Kelpie Express' on an inspection tour and Gidgee seems to love it. Jarah, on the other hand ain't so sure. Likes the idea, but not the jump.

Saturday, September 8, 2012

Flooring #1

Done!
All the joist are now in place.
TRIVIA: there are 936 screws holding down the floor joists.
Jim recons that with all the drilling his right arm is beginning to resemble. . .


 

Sunday, September 2, 2012

Up!

Last three main frames finally went up

 And look we have roof holdie-up stuff as well
Next task is to get all the flooring sections down.